Skip to main content

BR05: Alternate Route 58

Project Purpose

The purpose of this study will be to analyze the operational and safety issues identified along Alternate Route 58 between the Sugar Run Road/Eagle Ridge Drive and Cecil Street intersections in Lee County. The objective of this study is to identify cost-effective preferred improvement alternatives that address the deficient conditions.

Survey

The survey regarding potential transportation safety and operations improvements along Alternate Route 58 in Lee County between Sugar Run Road/Eagle Ridge Drive and Cecil Street is complete.

Study Partners

  • Lee County
  • LENOWISCO Planning District Commission
  • Mountain Empire Transit

Key Points of Contact

District Lead: Blake Ailor

Lead Consultant: Alex Shoemaker 

Schedule

PHASE DATES TASKS
Phase 1 August 2021 – September 2021 Problem Diagnosis/Brainstorm Alternatives
Phase 2 October 2021 – March 2022 Stakeholder/Public engagement and feedback
Phase 3 March 2022 – July 2022 Investment strategy cost estimation and refinement