HR02: Battlefield Boulevard and Great Bridge Bypass/Oak Grove Connector Interchange
Project Purpose
The purpose of this study will be to analyze the operational issues identified at the Battlefield Boulevard and Great Bridge Bypass/Oak Grove Connector (Route 168) interchange, with a focus on providing enhanced pedestrian, bicycle, and transit access. The surrounding area sees an influx of over 93,000 commuters, which places stress on the interchange and adjacent intersections - leading to significant congestion during AM and PM rush hours. Travel patterns at the interchange are also tied to operations on I-64. The objective of this study is to identify cost-effective preferred improvement alternatives that address the deficient conditions and provide connectivity to pedestrians, cyclists, and transit riders.
Survey
The survey regarding potential transportation improvements (safety, operational, bicycle/pedestrian and transit access) along Battlefield Boulevard between Gainsborough Square and Great Bridge Boulevard/Kempsville Road, including the Chesapeake Expressway (Route 168 Bypass) interchange, in Chesapeake is complete.
Study Partners
- City of Chesapeake
- Hampton Roads Transportation Planning Organization
Key Points of Contact
District Lead: Eric Stringfield/Jerry Pauley
Lead Consultant: Kimley-Horn
Schedule
| PHASE | DATES | TASKS |
|---|---|---|
| Phase 1 | August 2021 – September 2021 | Problem Diagnosis/Brainstorm Alternatives |
| Phase 2 | October 2021 – March 2022 | Stakeholder/Public engagement and feedback |
| Phase 3 | March 2022 – July 2022 | Investment strategy cost estimation and refinement |