HR02: Battlefield Boulevard and Great Bridge Bypass/Oak Grove Connector Interchange

Project Purpose

The purpose of this study will be to analyze the operational issues identified at the Battlefield Boulevard and Great Bridge Bypass/Oak Grove Connector (Route 168) interchange, with a focus on providing enhanced pedestrian, bicycle, and transit access. The surrounding area sees an influx of over 93,000 commuters, which places stress on the interchange and adjacent intersections - leading to significant congestion during AM and PM rush hours. Travel patterns at the interchange are also tied to operations on I-64. The objective of this study is to identify cost-effective preferred improvement alternatives that address the deficient conditions and provide connectivity to pedestrians, cyclists, and transit riders.  

Survey

The survey regarding potential transportation improvements (safety, operational, bicycle/pedestrian and transit access) along Battlefield Boulevard between Gainsborough Square and Great Bridge Boulevard/Kempsville Road, including the Chesapeake Expressway (Route 168 Bypass) interchange, in Chesapeake is complete.

Study Partners

  • City of Chesapeake
  • Hampton Roads Transportation Planning Organization

Key Points of Contact

District Lead: Eric Stringfield/Jerry Pauley 

Lead Consultant: Kimley-Horn

Schedule

PHASE DATES TASKS
Phase 1 August 2021 – September 2021 Problem Diagnosis/Brainstorm Alternatives
Phase 2 October 2021 – March 2022 Stakeholder/Public engagement and feedback
Phase 3 March 2022 – July 2022 Investment strategy cost estimation and refinement

Last updated: April 16, 2026