SA01: Route 11 (Williamson Road)

Project Purpose

The study objectives are to address vehicular and pedestrian safety and pedestrian, bicycle, and transit access concerns along the Route 11 (Williamson Road) corridor. One node and 11 segments were identified as VTrans Priority 1 needs along the study corridor, with seven additional segments identified as Priority 2 needs. Goals are to identify safety and operational improvements to improve safety and access for all transportation users.

Survey

The survey regarding potential transportation safety, bicycle, pedestrian and transit improvements along Williamson Road (Route 11) between Route 460 (Orange Avenue) and Hershberger Road (Route 101) is complete.

Study Partners

  • City of Roanoke

Key Points of Contact

District Lead: Michael Gray

Lead Consultant: Dana Trone

Schedule

PHASE DATES TASKS
Phase 1 August 2021 – September 2021 Problem Diagnosis/Brainstorm Alternatives
Phase 2 October 2021 – March 2022 Stakeholder/Public engagement and feedback
Phase 3 March 2022 – July 2022 Investment strategy cost estimation and refinement

Last updated: April 14, 2026