Route 460 (Orange Avenue) TO Route 101 (Hershberger Road)
The survey regarding potential transportation safety, bicycle, pedestrian and transit improvements along Williamson Rd. (Route 11) between Route 460 (Orange Ave.) and Hershberger Rd. (Route 101) is complete.
The project objectives are to address vehicular and pedestrian safety and pedestrian, bicycle, and transit access concerns along the Route 11 (Williamson Road) corridor. One node and 11 segments were identified as VTrans Priority 1 needs along the study corridor, with 7 additional segments identified as Priority 2 needs. Goals are to identify safety and operational improvements to improve safety and access for all transportation users.
District Lead: Michael Gray
Lead Consultant: Dana Trone
PHASE | DATES | TASKS |
---|---|---|
Phase 1 | August 2021 – September 2021 | Problem Diagnosis/Brainstorm Alternatives |
Phase 2 | October 2021 – March 2022 | Stakeholder/Public engagement and feedback |
Phase 3 | March 2022 – July 2022 | Investment strategy cost estimation and refinement |
Last updated: May 23, 2024